September 2014
Detailed exploration programme took place on Tailings project with more than 700 meters of drilling.


May 2015
Metallurgical testworks has been carried out for the tailings project in independent Russian and Canadian laboratories. More than 60% Sn concentrate has been achieved in gravity circuit.

June 2015
Company has received exploration permissions for three prospecting areas in Maly Khingan Area, covering almost 300 km2.
December 2015
Acquisition of license for exploration and mining on Centralnoye tin deposit with more than 3,8 thousand tonnes of tin.

March 2016
The company finalised the engineering survey for the preparation of the detailed design for the tailings project. The main state permits for construction have been obtained.

April 2016
Khingan Resources Limited took part in ITRI conference held in Peru. A number of MOU and pre-offtake agreements have been signed.

May 2016
Acquisition of license for Berezovskoye hard rock tin deposit. Estimated resource base is 16 thousand tonnes of Sn. Completion of Scoping studies for Centralnoye and Berezovskoye hard rock deposits development.

September 2016
Pilot processing testwork has been carried out on the Tailings project industrial site. More than 80 kg of 10% pre-concentrate has been achieved in gravity circuit and sent for laboratory flotation tests.

January 2018
Completion of the processing plant building. Installation of the main processing equipment

2020
Triple increase of the revenue stream for the current operational plant in Khingansk after the involvement of the ore from nearest Berezovskoye and Centralnoye tin deposits into the processing operations.

2019-2020
Confrirmation drilling programme
for Berezovskoye and Centralnoye deposits.


Today
June 2017
Launch of the concrete works on the tailings project. Main equipment purchase.

August 2018
Commissioning phase

February 2019
Shipment of the first container with 22 tonnes of 60% tin concentrate