September 27, 2017

 

Construction progress for the Tailings Project is ongoing.

By the end of August the earthworks contractor completed the piling for the process plant foundations.     

 

The electrical connection to the regional supply was completed during the month.

       

The footings for the steel columns, which will hold the framework for the process plant building, are being constructed. The contractor commenced work on the construction of the reservoir for technical and fire water supply and also the piling for the heating plant foundations.

 

General contractor John Tomas, head of design Yury Podkovyrov and the entire Board of Directors namely Martin Smith, Pavel Ustenko, Konstantin Kulakov and Anton Matveev visited the site from 17-25 September.